- 1、本文档共7页,可阅读全部内容。
- 2、原创力文档(book118)网站文档一经付费(服务费),不意味着购买了该文档的版权,仅供个人/单位学习、研究之用,不得用于商业用途,未经授权,严禁复制、发行、汇编、翻译或者网络传播等,侵权必究。
- 3、本站所有内容均由合作方或网友上传,本站不对文档的完整性、权威性及其观点立场正确性做任何保证或承诺!文档内容仅供研究参考,付费前请自行鉴别。如您付费,意味着您自己接受本站规则且自行承担风险,本站不退款、不进行额外附加服务;查看《如何避免下载的几个坑》。如果您已付费下载过本站文档,您可以点击 这里二次下载。
- 4、如文档侵犯商业秘密、侵犯著作权、侵犯人身权等,请点击“版权申诉”(推荐),也可以打举报电话:400-050-0827(电话支持时间:9:00-18:30)。
- 5、该文档为VIP文档,如果想要下载,成为VIP会员后,下载免费。
- 6、成为VIP后,下载本文档将扣除1次下载权益。下载后,不支持退款、换文档。如有疑问请联系我们。
- 7、成为VIP后,您将拥有八大权益,权益包括:VIP文档下载权益、阅读免打扰、文档格式转换、高级专利检索、专属身份标志、高级客服、多端互通、版权登记。
- 8、VIP文档为合作方或网友上传,每下载1次, 网站将根据用户上传文档的质量评分、类型等,对文档贡献者给予高额补贴、流量扶持。如果你也想贡献VIP文档。上传文档
查看更多
《解读排水管道工程施工质量管理重点及措施中英文
解读排水管道工程施工质量管理重点及措施中英文
Interpretation of drainage pipeline construction quality management focus and measures
从施工准备阶段、管道施工阶段、管线安装、检查井施工以及土方回填和闭水试验等方面论述了市政给排水管道工程施工质量管理重点及措施。
From the aspects of the construction preparation stage, construction stage, pipeline installation, pipeline inspection well construction and earthwork backfilling and closed water test of municipal water supply and drainage engineering construction quality management focus and measures.
一、 施工准备阶段质量控制
Quality control, construction preparation stage
(一)公共设施保护? 管道沟槽施工应根据土质情况采用支撑以免造成滑坡、塌方,若施工遇到建构筑物基础或电杆、灯杆等应制定防止下沉或变形措施后方可施工,一般应采用钢板桩加固方法;施工地区地下水量丰富则在管道施工过程中往往需要排水,应制定合理措施以保证地面不发生过大沉降而影响周围建构筑物使用安全;在埋有高压线地区内开挖时要求挖掘机不能在其正上方开挖,必要时采用人工开挖;开挖过程中遇到地下管线和各种构筑物应尽量迁移,若不能迁移应人工开挖使其外露之后采取吊托等加固措施。
( a ) public facilities protection? Pipeline trench construction should be based on soil conditions with support so as to avoid landslide, collapse, if in the construction of building foundation or pole, a lamp post should be developed to prevent sinking or deformation measures before the construction, should generally be used for steel sheet pile reinforcement method; construction area, the underground water is abundant in the pipeline construction process often need to drain, should make reasonable measures to ensure that the ground is not too large settlement of surrounding buildings safe use; buried in a high-voltage wire area excavation excavator is not in its just above the excavation, when necessary, using artificial excavation; excavation encountered in the process of underground pipelines and structures should as far as possible migration, if you cannot transfer should be excavated after the exposure to take reinforcement measures such as hanging bracket.
(二)道路拆除与恢复? 市政给排水管道施工必然涉及到一定路面的拆除与恢复工作,为了能够保证施工安全及路基质量,在道路开挖前应根据施工图纸计算开口宽度,用白漆标出开挖线之后用切割机将路面切断,用挖掘机对破碎的混凝土路面及碎石等垫层进行开挖并合理堆放以备后用,管路施工完成后的沟槽回填工作直接影响路面的质量及使用功能,尤其是在高原地区更应注重沟槽回填质量,一般对回填土或砂采用夯实或灌水密实,之后采用压路机分层碾压,回填应分层回填及夯实,并应控制每层回填厚度不超过25cm,夯实后采用核子密度仪测量密实度,待其压实