21、配网变压器监测计量终端安装作业指导书PWZDH01汇编
第 8 部分:配网工程
配网变压器监测计量终端安装 作 业指 导书
编码:PWZDH-01
目 次
1 适用范围 ······················································································································································ 2
2 编写依据 ······················································································································································ 2
3 作业流程图 ·················································································································································· 2
4 安全风险辨析与预控 ·································································································································· 3
5 作业准备 ························································································································································ 4
6 作业方法 ··························································································································································5
7 质量控制措施及检验标准 ······························································································································ 6
1 适用范围
1.1 电压等级
35kV 及以下配网工程。
1.2 电气类别
配网变压器监测计量终端安装。
2 编写依据
表 2 编 写 依 据
序号
引用资料名称
1
GB 50171—1992《电气装置安装工程盘、柜及二次回路结线施工及验收规范》
2
DL/T 5161.1—2002《电气装置安装工程质量检验及评定规程 第 1 部分:通则》
DL/T 5161.8—2002《电气装置安装工程 质量检验及评定规程 第 8 部分:盘、柜及二次回路结线施工质量检 验》
3
Q/CSG 10017.2—2007《110kV~500kV 送变电工程质量检验及评定标准 第 2 部分:变电电气安装工程》
4
Q/CSG 11105—2008《南方电网工程施工工艺控制规范》
5
《中国南方电网有限责任公司基建工程质量控制作业标准(WHS)》
3 作业流程图
图 3 作业流程图
4 安全风险辨析与预控
4.1 配网变压器监测计量终端安装前,施工项目部根据该项目作业任务、施工条件,参照《电网建 设施工安全基准风险指南》(下简称《指南》)开展针对性安全风险评估工作,形成该任务的风险分析表。
4.2 按《指南》中与配网变压器监测计量终端安装相关联的《电网建设安全施工作业票》(编码: PWZDH-01-01/01),结合现场实际情况进行差异化分析,确定风险等级,现场技术员填写安全施工作业票, 安全员审核,施工负责人签发。
4.3 施工负责人核对风险控制措施,并在日站班会上对全体作业人员进行安全交底,接受交底的作业
人员负责将安全措施落实到各作业任务和步骤中。
4.4 安全施工作业票由施工负责人现场持有,工作内容、地点不变时可连续使用 10 天,超过 10 天须 重新办理作业票,在工作完成后上交项目部保存备查。
表 4.1 作 业任 务 安 全 基准风 险 指南
序号
危 害 名 称
风险种类
风险等级
风险控制措施
1
邻近带电设备施工无安 全措施