年度天然气输配工
冬 季 施 工 方 案
编制:
审核:
批准:
项目部
年11月1 日
学习 参考 资料 分享
WORD 格式 整理
目 录
一、编制原则及依据·········································1
二、施工部署···············································1
三、施工技术措施··········································2
1、土方开挖··············································2
2、管材拉运及下沟········································2
3、钢管焊接安装··········································2
4 、管线防腐补口、补伤····································4
5、PE 管焊接施工技术措施································ 4
6、管道吹扫、试压········································5
7 、土方回填··············································5
8、阀井砌筑··············································5
9、其他措施··············································7
四、冬季施工安全管理保证措施·······························8
五 、 消 防 保 证 措
施···········································10
学习 参考 资料 分享
WORD 格式 整理
学习 参考 资料 分享
WORD 格式 整理
一、编制原则及依据
(1)编制原则:
1、依据施工合同要求,确保施工工期、质量、安全等满足业主
要求的原则。
2、优化施工组织方案、施工工艺和施工方法,确保工程质量达
到合同及国家验收规范要求的原则。
(2 )编制依据:
1、工程承包施工合同;
2、施工图纸;
3、《建筑工程冬季施工规范》 JGJ104-2011
4 、《城镇燃气设计规范》 GB50028-2006
5、《城镇燃气技术规范》 GB50494-2009
6、城镇燃气室内工程施工质量验收规范 CJJ94-2009
7 、《城镇燃气输配工程施工及验收规范》 CJJ33-2005
8、《现场设备、工业管道焊接工程施工及验收规范》GB50236-98
9、施工现
您可能关注的文档
- 游泳池防水施工组织设计方案.pdf
- 湖北导游基础知识试题1.pdf
- 湖北省2019-2020七年级下学期期末考试数学试题1.pdf
- 湖北省2017-2018学年高二下学期期末阶段摸底调研联合考试化学试题.pdf
- 湖北省2019-2020中考英语模拟试卷(含答案).pdf
- 湖北省2019中考英语模拟试卷(含答案).pdf
- 湖北省八校2019届高三3月第二次联考理综化学试题 word版.pdf
- 湖北省天门、仙桃等八市2019届高三3月第二次联合考试理综化学试题.pdf
- 湖北省孝感市2018-2019高一下学期期中考试化学试卷.pdf
- 湖北省孝感市七校教学联盟2016-2017学年高二上学期期中考试化学试卷.pdf
文档评论(0)