1. You are the project manager for an outdoor concert event scheduled for 1 year from today. Youre working on the procurement plan for the computer software program that will control the lighting and screen projections during the concert. Youve decided to contract with a professional services company that specializes in writing custom software programs. You want to minimize the risk to the organization, so youll opt for which contract type? A. Fixed price incentive fee B. Cost plus fixed fee C. Firm fixed price D. Cost plus incentive fee 你是一场的户外音乐会的项目经理,该活动1 年后的今天举行。你正在制定采购计划, 该计划是关于用于控制音乐会灯光和