- 1、本文档共20页,可阅读全部内容。
- 2、原创力文档(book118)网站文档一经付费(服务费),不意味着购买了该文档的版权,仅供个人/单位学习、研究之用,不得用于商业用途,未经授权,严禁复制、发行、汇编、翻译或者网络传播等,侵权必究。
- 3、本站所有内容均由合作方或网友上传,本站不对文档的完整性、权威性及其观点立场正确性做任何保证或承诺!文档内容仅供研究参考,付费前请自行鉴别。如您付费,意味着您自己接受本站规则且自行承担风险,本站不退款、不进行额外附加服务;查看《如何避免下载的几个坑》。如果您已付费下载过本站文档,您可以点击 这里二次下载。
- 4、如文档侵犯商业秘密、侵犯著作权、侵犯人身权等,请点击“版权申诉”(推荐),也可以打举报电话:400-050-0827(电话支持时间:9:00-18:30)。
- 5、该文档为VIP文档,如果想要下载,成为VIP会员后,下载免费。
- 6、成为VIP后,下载本文档将扣除1次下载权益。下载后,不支持退款、换文档。如有疑问请联系我们。
- 7、成为VIP后,您将拥有八大权益,权益包括:VIP文档下载权益、阅读免打扰、文档格式转换、高级专利检索、专属身份标志、高级客服、多端互通、版权登记。
- 8、VIP文档为合作方或网友上传,每下载1次, 网站将根据用户上传文档的质量评分、类型等,对文档贡献者给予高额补贴、流量扶持。如果你也想贡献VIP文档。上传文档
查看更多
大桥施工(国外英文资料)
大桥施工(国外英文资料)
Bridge construction
There are 1 bridges in this section, that is, the rock bridge, the center post No. K110+268, is a span of 30 meters of T beam structure, the bridge length of 156 meters. The upper bridge is simply supported to continuous prestressed T beam, the lower beam, column, beam, floor, bored pile foundation. Project number: T beam 60, pile 32, 12 beam, 16 columns.
Drilling data show that the soil under the riverbed is sandy soil and gravel soil, and the bedrock is weakly weathered shale.
Set the bridge in the left of the line.
The main construction schedule is from January 1, 2003 to April 1, 2004.
(1) construction of bored piles;
The contract section has 32 bored piles, and the diameter is 180cm and 120cm, all of them are rock socketed piles. It is scheduled for completion in March 2003 10.
According to the geological condition at the bridge site of the bid section, the drilling equipment for the bored pile construction adopts impact drilling, and the individual short bored pile can be used as a rotary drilling rig (with a roller bit). The use of a crane reinforcement cage, concrete concrete mix automatic metering and mixing station, concrete transporting trucks concrete chute with tremie concrete. In order to avoid the pollution of the river, set the mud pool, the mud into the mud pool, after precipitation by pile completion, digging mud, stone for fill river flow.
The construction procedure of bored concrete for embedment of steel casing, driller, rushed (drilling), the first clear hole, reinforcement cage, concrete pipe under second, clear the pile to pile head and pile foundation inspection chiseling concrete into the hole, pouring underwater.
Construction process see Figure 5-3 bored pile construction process flow chart
1, pile location, drill in place
The site of the bridge site is leveled, the sundries are removed, the soft soil is replaced, and the compaction is compacted. The total station instrument is used to accurately measure th