- 1、原创力文档(book118)网站文档一经付费(服务费),不意味着购买了该文档的版权,仅供个人/单位学习、研究之用,不得用于商业用途,未经授权,严禁复制、发行、汇编、翻译或者网络传播等,侵权必究。。
- 2、本站所有内容均由合作方或网友上传,本站不对文档的完整性、权威性及其观点立场正确性做任何保证或承诺!文档内容仅供研究参考,付费前请自行鉴别。如您付费,意味着您自己接受本站规则且自行承担风险,本站不退款、不进行额外附加服务;查看《如何避免下载的几个坑》。如果您已付费下载过本站文档,您可以点击 这里二次下载。
- 3、如文档侵犯商业秘密、侵犯著作权、侵犯人身权等,请点击“版权申诉”(推荐),也可以打举报电话:400-050-0827(电话支持时间:9:00-18:30)。
- 4、该文档为VIP文档,如果想要下载,成为VIP会员后,下载免费。
- 5、成为VIP后,下载本文档将扣除1次下载权益。下载后,不支持退款、换文档。如有疑问请联系我们。
- 6、成为VIP后,您将拥有八大权益,权益包括:VIP文档下载权益、阅读免打扰、文档格式转换、高级专利检索、专属身份标志、高级客服、多端互通、版权登记。
- 7、VIP文档为合作方或网友上传,每下载1次, 网站将根据用户上传文档的质量评分、类型等,对文档贡献者给予高额补贴、流量扶持。如果你也想贡献VIP文档。上传文档
查看更多
箱涵工程施工方案(国外英文资料)
箱涵工程施工方案
Construction scheme of box culvert project
I. General Situation of K30+381 box culvert.
The box is 1-6 * 3 box culvert, and route direction angle of 800, Han long 37.29m, C30 concrete 373.74m3, I reinforced 1753.8kg, II reinforced 42316.6kg the box culvert project started in 20XX in August 25th, 20XX completed in September 25th.
Two, culvert construction program.
1, technical preparation.
1) construction lofting. The conductor points approved by the supervision engineer shall be arranged according to the design requirements, and the position of the center and the axis of the box culvert shall be determined by using the total station instrument by means of coordinate method.
2) sand, stone, cement, steel and so on, need to pass the laboratory test qualified.
3) the concrete ratio is approved by the supervision engineer.
4) technical explanation to the construction team.
2, construction process.
1) construction lofting. The location of the center and the axis of the culvert is measured by the total station instrument, so as to protect the staking out site. According to the design and construction needs, a range of foundation pit excavation, excavation of the lime line mark. Report the lofting result to the supervision engineer.
2) excavation. The excavation of the foundation pit is mainly based on the excavator and supplemented by the artificial. Excavator excavation
After approaching the design elevation, the remaining quantities are leveled by manual excavation to accurately control the elevation of the culvert. When underground seepage occurs on the foundation, the drainage ditch is dug at the bottom of the base section, and the drainage measures are concentrated, and a special person is arranged to carry out drainage work during the whole construction process. Substrate handling shall be tested to ensure that the base bearing capacity is not less than 111Kpa. According to the design, lay 30 cm thick gravel cushion on the base and tamp with a small tampin