广州南部地区快速路(仑头~龙穴岛)SD5标 珠江特大桥(138+250+138)m预应力连续刚构 边跨合拢段及中跨合拢段施工工艺 编制: 审核: 批准: 中铁大桥局集团第三工程有限公司 珠江特大桥项目部 二00四年八月三十日 目 录 一、工程概况············································1 二、编制依据············································2 三、工艺流程············································3 四、合拢段各分项工程及施工工艺要求······················5 五、安全保证措施········································12 六、工期要求············································13 七、质量保证体系········································13 1.工程概况 1.1珠江特大桥主桥为(138+250+138)mPC连续—刚构,双向八车道,单幅箱梁宽度为16.5m,全幅桥宽为34m。主桥连续—刚构采用挂篮悬臂浇注法施工,每墩共29个对块。边跨直线段长为11.7m,采用落地支架法施工(修建临时支墩,上