南开大学 13春学期《工程施工》在线作业(Nankai University spring 13 semester project construction online homework)
南开大学 13春学期《工程施工》在线作业(Nankai University spring 13 semester project construction online homework)
13 spring semester project construction online homework
1. known P work has a tight work after G, G the latest finish time is fourteenth days and the duration of 3 days, the total float for the first P 2 days for sixth days, the duration is l days, P work for free float (days)
A. 1
B. 2
C. 3
D. 4
The correct answer: B Full Score: 2 points: 2
2. in the network planning, the total time of H work for 3 days, a total of three H J, K, tight L, J the earliest start time and latest start time is twenty-first days and twenty-second days, the earliest completion time of job K and latest finish time was twenty-third and twenty-fifth days L the earliest start time and latest start time were twenty-first days and twenty-third days, is the work of H (day) for free float
A. 1
B. 2
C. 3
D. 4
The correct answer: B Full Score: 2 points: 2
3. for the network of double code time scales drawn by the computation period, the following statement is incorrect
A. in addition to the network starting point, each nodes timescale is the earliest completion time of a job
B. in addition to the network endpoint, each nodes timescale is the earliest start time of a job
C. the total time difference is not zero, and the horizontal projection length of the arrow on the time axis is not equal to the duration of the work
D. wave arrow points at the node not just an arrow node
The correct answer: C Full Score: 2 points: 2
4. the strength of the lower member concrete and the strength of the lower member concrete shall be reduced to the design strength by means of the precast precast concrete pile
A. 20%
B. 30%
C. 40%
D. 50%
The correct answer: B Full Score: 2 points: 2
5. the construction of pre tensioned prestressed concrete. When the prestressed steel bar is relaxed, the strength of concrete should not be less than the design intensity grade
A. 75%
B. 80%
C. 85%
D. 100%
The correct answer: A Full Score: 2 poi
您可能关注的文档
- 农林学-我国玉米深加工面临的问题及对策研究81587(Agriculture and forestry - problems and Countermeasures of maize deep processing in China 81587).doc
- 农林学-我国玉米深加工面临的问题及对策研究(Agriculture and forestry - problems and Countermeasures of maize deep processing in China).doc
- 农村社会化服务(Rural social service).doc
- 农林经济管理(渔业经济管理)专业培养方案(Professional training program for agricultural and forestry economic management (fishery economic management)).doc
- 农林学-美国玉米深加工经验对我国的启示(Agriculture and forestry - American corn deep processing experience and Its Enlightenment to China).doc
- 农林学-我国都市农业的发展模式研究(Agriculture and forestry - A Study on the development model of urban agriculture in China).doc
- 农民工子女教育问题的困境、成因及对策(The plight, causes and Countermeasures of the education of migrant workers' children).doc
- 农民工医疗保障问题的法学思考_对策(Law thinking of the medical problems of migrant workers _ Countermeasures).doc
- 农民工返乡潮下的基层治理困境(The Grassroots Governance Dilemma of migrant workers returning home).doc
- 农法耕种(Farming).doc
原创力文档

文档评论(0)