年产400万吨渣油加烃装置施工方案
2200万吨/年炼油改扩建及100万吨/年乙
烯工程工程
400万吨年渣油加氢装置炉区基础/
施
工
方
案
编制:
审核:
批准:
xx建筑安装工程有限责任公司
2014年11月22 日
目录
第一章 工程概况 ··················································1
1、编制依据······················································1
2、工程概况······················································1
第二章 施工准备和施工总体部署 ····································2
1、施工组织框架··················································2
2、技术准备······················································3
3、材料准备 ······················································4
4、机械及仪器准备················································4
5、临时进度用水、用电准备 ·········································5
6、施工进度计划 ···················································5
第三章 混凝土结构施工技术要求 ····································6
一、测量技术要求·················································6
二、模板制安技术要求·············································6
三、钢筋制安技术要求 ·············································9
四、混凝土施工技术要求···········································11
第四章 400万吨/年渣油加氢装置炉基础施工方法 ·····················12
一、施工流程 ·····················································12
二、施工工艺及方法 ···············································12
第五章 成品保护主要施工方法 ·····································17
第六章 质量保证体系及措施 ·······································18
一、工程质量管理体系············································18
二、质量控制程序················································19
三、质量检测体系 ················································20
第六章 施工HSE部分 ············································22
一、施工安全组织结构············································22
二、安全保证措施················································22
三、现场文明施工管理措施 ···