- 1、原创力文档(book118)网站文档一经付费(服务费),不意味着购买了该文档的版权,仅供个人/单位学习、研究之用,不得用于商业用途,未经授权,严禁复制、发行、汇编、翻译或者网络传播等,侵权必究。。
- 2、本站所有内容均由合作方或网友上传,本站不对文档的完整性、权威性及其观点立场正确性做任何保证或承诺!文档内容仅供研究参考,付费前请自行鉴别。如您付费,意味着您自己接受本站规则且自行承担风险,本站不退款、不进行额外附加服务;查看《如何避免下载的几个坑》。如果您已付费下载过本站文档,您可以点击 这里二次下载。
- 3、如文档侵犯商业秘密、侵犯著作权、侵犯人身权等,请点击“版权申诉”(推荐),也可以打举报电话:400-050-0827(电话支持时间:9:00-18:30)。
- 4、该文档为VIP文档,如果想要下载,成为VIP会员后,下载免费。
- 5、成为VIP后,下载本文档将扣除1次下载权益。下载后,不支持退款、换文档。如有疑问请联系我们。
- 6、成为VIP后,您将拥有八大权益,权益包括:VIP文档下载权益、阅读免打扰、文档格式转换、高级专利检索、专属身份标志、高级客服、多端互通、版权登记。
- 7、VIP文档为合作方或网友上传,每下载1次, 网站将根据用户上传文档的质量评分、类型等,对文档贡献者给予高额补贴、流量扶持。如果你也想贡献VIP文档。上传文档
查看更多
热风炉耐材施工安装指导说明书2(英文版)
上接:文库中
《热风炉耐材施工安装指导说明书1(英文版).doc》
3.4.2 Laying of Stove Bottom with Clay Brick
1) The bricklaying shall start from the center to both sides by scribing the level line as per the design elevation on the cross central line.
2) Quality Inspection: leveling instrument
Fig. 3.4-3 Schematic Diagram for Sequence of Clay Brickwork
3.4.3 Paving of Fused Sand
1) The dry sand with maximum particle diameter below 5mm shall be paved on the clay bricks according to the design elevation.
2) The large screw rod built around shall be covered with the rainproof cloth and bound tightly with steel wire.
3) This work has something to do with installation of stove shell for Section 1. The stove shell for the 1st section being hoisted, the rainproof cloth shall be removed. Following inspection of stove shell elevation after hoisting, the stove shell for the 1st section shall be hoisted again to inspect whether the surface of fused sand has the drop pit. If there is the drop pits, they shall be re-leveled with fused sand. Such an inspection shall be repeated until the flatness is competent.
3.4.4 Packing of Water-free Tamping
After the stove shell for the 3rd section is installed, the explosive shall be packed with tamping. The tamping shall be pressed to pack the lower part of the stove shell. And the redbrick shall be laid close to the stove shell to block off the water-free tamping. The surface of redbrick shall be plastered with a 20mm-thick layer of 1:2 cement mortar.
3.4.5 Pressure Grouting
1) Following the welding of strengthening ring and beam on the lower part of stove shell and the fastening of bolts, the pressure grouting can start after the stove shell is installed to the 6th section. Prior to hoisting of the stove bottom shell, the stub pipe shall be welded and embedded.
Fig. 3.4-4 Schematic Diagram of Grouting Stub Pipe
2) The injection mix is the 425# ordinary Portland cement and the water-cement ratio 0.4~0.5.
3) Before pressure grouting, the grouting holes shall be