预应力管监理实施细则

XXXX五期(高层区)工程 预应力管桩 监理实施细则 XXXX 工 程 咨 询 有 限 公 司 XXXX项目监理部 二 零 年 月 目 录 一、编制依据············································1 二、概述及概况········································1-6 三、实施监理的目标和范围································6 四、监理依据···········································6-7 五、监理工作控制要点··································7-9 六、压桩施工流程监理控制要点···························10-12 七、压桩易出现的质量通病及处理措施·····················12-14 八、监理工作流程·······································14-18 一、编制依据 1、XXXX项五期(高层区)桩基工程有关设计图纸。 2、国家和地方有关工程建设的法规,法律和规章 国家《建设监理规范》 ≤建筑工程施工质量验收统一标准≥(GB50300-2001) ≤建筑地基基础工程施工质量验收规范≥(G