Question 155: You have finished putting together your project budget and notice that there is a point at which cost and staffing levels are highest. At which point in the project would this generally be?CA: Starting the project.B: Organizing and preparing. C: Carrying out the work.D: Closing the project.Question 156: You are completing the work of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline. What PMBOK? Guide process are you completing?DA: Cost Performance Baseline (基线;底线)B: Estimate CostsC: Control CostsD: Determine Budget