- 1、原创力文档(book118)网站文档一经付费(服务费),不意味着购买了该文档的版权,仅供个人/单位学习、研究之用,不得用于商业用途,未经授权,严禁复制、发行、汇编、翻译或者网络传播等,侵权必究。。
- 2、本站所有内容均由合作方或网友上传,本站不对文档的完整性、权威性及其观点立场正确性做任何保证或承诺!文档内容仅供研究参考,付费前请自行鉴别。如您付费,意味着您自己接受本站规则且自行承担风险,本站不退款、不进行额外附加服务;查看《如何避免下载的几个坑》。如果您已付费下载过本站文档,您可以点击 这里二次下载。
- 3、如文档侵犯商业秘密、侵犯著作权、侵犯人身权等,请点击“版权申诉”(推荐),也可以打举报电话:400-050-0827(电话支持时间:9:00-18:30)。
- 4、该文档为VIP文档,如果想要下载,成为VIP会员后,下载免费。
- 5、成为VIP后,下载本文档将扣除1次下载权益。下载后,不支持退款、换文档。如有疑问请联系我们。
- 6、成为VIP后,您将拥有八大权益,权益包括:VIP文档下载权益、阅读免打扰、文档格式转换、高级专利检索、专属身份标志、高级客服、多端互通、版权登记。
- 7、VIP文档为合作方或网友上传,每下载1次, 网站将根据用户上传文档的质量评分、类型等,对文档贡献者给予高额补贴、流量扶持。如果你也想贡献VIP文档。上传文档
查看更多
欧亚路道口整修的施工组织设计
欧亚路道口整修施工组织设计
永煤公司铁路运输处
目 录
1工程概况···················································································3
2 工程施工组织·········································································3
2.1组织机构··············································································3
2.2劳力组织···············································································3
2.3时间安排···············································································3
2.4施工流程···············································································4
2.5施工说明···············································································6
3施工防护措施……···································································6
4施工所需机具、材料·······························································7
4.1 施工所需机械、工器具························································7
4.2 施工所需材料······································································8
5工程概算···················································································9
5.1人工费···················································································9
5.2机械租用费···········································································9
5.3税费·······················································································9
5.4材料费···················································································9
欧亚路道口整修施工组织设计
1工程概况
欧亚路道口全长44米,位于陈四楼矿铁路专用线DK38+027处,中间26.4 米铺设路面为橡胶道口板,两侧各 8.8米为混凝土道口板,由于该道口通车辆较大,造成道口线路病害严重,经检查发现轨距方向高低不良,给行车安全带来危害。根据工作计划安排,现需对该道口进行整修。此工程由工务段负责组织施工。
2 工程施工组织
2.1组织机构
郑伟负责施工全面管理与协调工作,为施工总负责人;徐强负责现场技术指导;李亚峰负责后勤保障;李庄工区工长杜国昌(手机号负责现场劳力组织及施工作业;副工长李金华负责安全防护。
2.2劳力组织:
施工人员由李庄工区,车集工区人员组成。
2.3时间安排
2.3.1计划工期5天,第1天准备材料;第2天施工北侧22米路面;第3天安装北侧路面减速带和铺设道口板;第4天施工南侧22米路面;第5天安装北侧路面减速带和铺设道口板。
2.3.2所有施工人员和租用机械与施工当日上午6点准时到现场,做好施工准备。施工当日,请电务段安排有关人员配合施工(有光缆和连接线)。
2.4施工流程
2.4.1施工前准备工作:
序号 工作内容 任务完成截止时间 责任
单位 任务要求 1 联系风镐、挖掘机、汽车、改装车 施工前2天 供应科 2 联系水钻 施工前2天 供应科 3 水泥、黄沙、石子 施工前2天 供应