友谊大桥装高压电缆工程施工计划资料.docVIP

  • 1
  • 0
  • 约1.13万字
  • 约 26页
  • 2019-05-13 发布于湖北
  • 举报

友谊大桥装高压电缆工程施工计划资料.doc

友谊大桥装高压电缆工程施工计划资料

C.E.M Supply and Installation of 220kV Cable Tray System at Amizade Method statement Scope of Works The Works to be carried out under this Contract comprise, but not limited to, the following: Supply and installation of the cable tray system including cable ladder, supports and all necessary accessories for 2 circuits of 220kV cables to be installed under the “Ponte da Amizade”; Supply and installation of the catwalk with supports and all necessary accessories along the cable trays; Construction of reinforced concrete cable transition pit at Macau side and Taipa side respectively; Installatio

文档评论(0)

1亿VIP精品文档

相关文档