- 1、原创力文档(book118)网站文档一经付费(服务费),不意味着购买了该文档的版权,仅供个人/单位学习、研究之用,不得用于商业用途,未经授权,严禁复制、发行、汇编、翻译或者网络传播等,侵权必究。。
- 2、本站所有内容均由合作方或网友上传,本站不对文档的完整性、权威性及其观点立场正确性做任何保证或承诺!文档内容仅供研究参考,付费前请自行鉴别。如您付费,意味着您自己接受本站规则且自行承担风险,本站不退款、不进行额外附加服务;查看《如何避免下载的几个坑》。如果您已付费下载过本站文档,您可以点击 这里二次下载。
- 3、如文档侵犯商业秘密、侵犯著作权、侵犯人身权等,请点击“版权申诉”(推荐),也可以打举报电话:400-050-0827(电话支持时间:9:00-18:30)。
- 4、该文档为VIP文档,如果想要下载,成为VIP会员后,下载免费。
- 5、成为VIP后,下载本文档将扣除1次下载权益。下载后,不支持退款、换文档。如有疑问请联系我们。
- 6、成为VIP后,您将拥有八大权益,权益包括:VIP文档下载权益、阅读免打扰、文档格式转换、高级专利检索、专属身份标志、高级客服、多端互通、版权登记。
- 7、VIP文档为合作方或网友上传,每下载1次, 网站将根据用户上传文档的质量评分、类型等,对文档贡献者给予高额补贴、流量扶持。如果你也想贡献VIP文档。上传文档
查看更多
监理周报
Jianli Weekly Report
工程名称:焊接器材(威海)有限公司厂房工程 日期(Date:):2007.08、07
Project name : EV project 编号(Serial Number):06
本周概况
General Situation
of This Week
1, beam and slab formwork installation of office building level 3 was done. Steel bar fabrication and installation of beam was done as well.
1:办公楼三层楼面梁、板模板支设,梁钢筋制作、安装;
2, east side retaining wall construction was in progress.
2:东面挡土墙毛石墙施工;
3, backfill of warehouse foundation was done.
3:厂房基础内回填土方;
4, wall and slab concrete pouring was done of water tank.
4:消防水池墙板混凝土施工
5, wall and slab steel bar installation and formwork installation of water tank were done.
5:消防游水池墙板钢筋安装、模板安装;
本周进度
情况
Progress of This Week
1,column steel bar installation of office building level 3 was in progress. And formwork installation was in progress.
1:办公楼进入三层柱钢筋安装阶段。模板支架搭设阶段’;
2, short column of warehouse foundation was almost done. Foundation bolts installation was almost done.
2:厂房基础短基本结束,钢构地脚螺栓安装基本结束;
3, east side retaining wall construction was in progress.
3:东侧挡土墙正在施工中,
4, wall and slab concrete pouring of water tank was done.
4:消防水池墙板混凝土结束;
5, backfill of warehouse foundation was done.
5:主厂房基础已回填土方;
施工质量情况
Construction
Quality Situation
1, mortar of retaining did not meet requirement and WJ was asked to redo.
1:挡土墙施工质量砂浆灌缝不够密实,;已要求总包加强管理, 对不合格的地方要作返工处理;
2, big area backfill was done by big equipment and corner should be paid more attention.
2::回填土大面积为机械回填,对角落及难点处人工回填,并采用打夯机夯实,
3, steel binding did not meet requirement and WJ has redone. ;
3;水池钢筋绑扎、钢筋之间的间距不符合规范要求,总包已整改,符合要求;
4, concrete pouring of water tank met requirement.
4:水池混凝土施工符合要求
5, concrete after check was commercial concrete and intensity level was C30 which complied with design requirement.
5:混凝土检查为商品混凝土,强度等级:C30,与设计要求一致;
6, concrete curing was done after 24 hours of pouring.
6:浇灌后24小时进行了浇水保养;
7, steel type, size, grade and quantity met design requirement.
7:钢筋安装的品种、规格、级别、数量符合设计
您可能关注的文档
最近下载
- 湖北省武汉市常青联合体2025-2026学年高二上学期期中联考数学试题(附解 .pdf VIP
- 财务出纳招聘信息范文 .pdf VIP
- 幼儿园大班美术《秋天的树叶》 优质课件.ppt VIP
- 输送机械 检查与维护规范 第1部分:带式输送机.pdf VIP
- 行波电子直线加速器自动频率控制(AFC)系统:原理、设计与实践.docx VIP
- 烹饪专业职业生涯规划书.docx VIP
- 互联网信息审核操作规程.docx VIP
- MT7815B-16B-16BD-17BD系列设计指南-Rev1.0.pdf VIP
- 2025年广西专业技术人员继续教育公需科目考试题库及答案(可考95分以上).docx
- 九年级期中考试家长会课件.ppt VIP
原创力文档


文档评论(0)