Software Commissioning Check List for Software Commissioning Hardware commissioning is completed. Download user program. Eliminate stop errors. Step-by-step function test of the system. Document program modifications. Save and archive program. Downloading the User Program to the CPU Eliminating Stop Errors Step-by-Step Function Test of the System Scan cycle FC 1 FB 4 DB 4 Hardware interrupt Cyclic interrupt Startup 1 2 3 4 5 6 7 8 x Sequence for program test Documenting Program Modifications Documentation using Object Properties (S7 program) Archiving a Project Properties of the project