China Project Team Status Report 05 17 2007 Agenda Review of Project Plan and Progress Update on Action Items New Issues Program Progress / Status Solution/Configuration: Waiting for Key configuration to be transported to DEV420 Assign purchase organization to plants. Currency exchange rate. COE team is reviewing IM output configuration RICEF: Standard Chinese physical Inventory form will be used. Waiting for pre-print form (Vendor promised the delivery date is next Monday) The customer size form still pending in COE Basis team Data Conversion: Material data basic/PP view GZ/SZ/ZJ 80% finish