Kraft Foods Inc.PEMB Structure Works 卡夫食品预制钢结构安装工程 PRODUCTION BUILDING ERECTION 生产厂房吊装方案 Date of Issued):2013-12-16 Author/Signature: JEFF QIAN Approver/Signature:XU YILONG 1-29轴 吊装前期要求 requirement for erection prophase 在材料进场前,做好现场的地坪保护工作,虽然业主已经在二楼的地面上采取15mm木板保护措施,但是为了不损坏地面,我公司对木板上进行二次保护,采取用3MM厚度的橡胶板进行铺设 In the material before entering good site floor protection, owners 15mm wood protection measures taken in the second floor on the ground, but in order not to damage the ground, my company on the board for secondary protection, taken with3MM thickness of the rubber sheet laying, 堆场位置原则以满足施工要