GC8.1 Contractor shall commence work on the XXCoal-fired Thermal Power Plant right after the Effective Date
承包商应该XX燃煤火电厂The Contract shall enter into full force and become effective on the date when all of the following conditions have been fulfilled:
以下条件满足后,合同才能全面生效:
this Contract Agreement has been signed for and on behalf of YY and the Contractor;
YY集团和承包商代表签署合同协议。
The Bidder has submitted to YY the Performance Security and Advance Payment Guarantee ;
投标商向YY集团支付履约保函和预付款保函。
The Bidder has received the Advance Payment from YY in accordance with relevant terms of the Contract.
投标商根据合同条款的规定,从YY集团收到预付款。 GC11.2 The price shall be fixed 合同总价固定 GC13.3 Amount of Performance Bond is 10% of Contract price 履约保函是合同总价格的10% GC25.2.2
Period during which the Guarantee Test should be conducted following commissioning: first test before Reliability Run, second and third test between start Reliability Run and within 3 months after PAC.
性能实验在调试后进行:第一次在可靠性运行前进行,第二次和第三次(如有)在可靠性运行开始至PAC后三个月期间。
GC26.2
` Liquidated Damages for delay in Time for Completion of each Unit of XXPower Plant will be 120,000USD/day of delay for each unit from the guaranteed Date of Completion or from the date resulting from an Extension of Time for Completion granted in accordance with GC 39, up to a maximum of 10% of the contract price.
对于XX燃煤火电厂120,000 USD/天,总违约赔偿金不得超过合同总价格的10%。
GC28.2 (b)
Liquidated Damages payable upon failure to meet Performance Guarantees未达到性能担保的要求,需要支付的违约赔偿金是:
The Contractor shall pay to YY for Liquidated Damages as stipulated in Appendix 8 of the Contract Agreement. Liquidated Damages for failure to meet the Performance Guarantees shall be 20% of the Contract Value as maximum. Total aggregate liability for all liquidated damages as stipulated in GC26.2 and GC28.2 in this contract shall not exceed 20% of contract price.
承包商向YY集团支付的违约赔偿金在附录8(合同协议)中有规定,性能担保的最高违约赔偿金是合同总价格的20%。本合同GC26.2 和GC28.2范围类所有的违约赔偿金的累计金额不得超过合同总价格的20%。
APPENDIX 3 (GC) - INSURANCE REQUIREMENTS
附件3 (GC) –