2.1 ECC Acceptance Report RABIGH 2 x 660 MW IPP PROJECT SAUDI ARABIA owner: consultant: contractor: ERECTION COMPLETION CERTIFICATE The erection of the System/Subsystem package has been completed within the boundaries or terminal points specified. . Title AIR COMPRESSOR FOR INSTRUMENT BOUNDARIES OR TERMINAL Refer to marked-up Drawing in Subsection 1.2 SUPPORTING DOCUMENTATION Refer to Section 4.0 for the related documentation Notice is hereby given to all parties that from 16:00 hours on 9/04/2012 Initial startup activities to commence on this equipment. The System/Subs