Planning Phase 1. The first step is to Brainstorm all the tasks that are required to complete the project. Some of the tasks may be subsets of others so there may be a need to review and organise the list created. 2. Identify how the tasks link together by identifying the predecessors. 3. Estimate the duration for each activity. Where you are unable to confidently predict the duration of any of the tasks, break the task down to more detail activities that can be more readily predicted. 4. Identify the person that will be responsible for ensuring the task is completed. 5. Using the informat