23. 481 Final closure

CE 481 - Final Closure Jeff Kuo, Ph.D., P.E. (CSUF) CE 481 - Final Closure Jeff Kuo, Ph.D., P.E. jkuo@fullerton.edu Introduction Final closure: closure of all hazardous waste management units (WMUs) at a given facility Post closure: For a disposal site, a 30-year period after closure (monitoring and maintenance to maintain integrity of the containment). Closure Plan - Content Post-closure Requirements The post-closure plan addresses Monitoring and maintenance of the facility or unit (mowing, fertilizing, reseeding, etc.) Name of responsible person during the post-closure care period Filing of