4250TEU-主应配电板系统系泊试验程序

MAIN SWITCHBOARD TEST PROCEDURE 1. Reference document main switch board diagram. Monitoring and alarm list. 2 . Test condition The diesel generator sets test is accepted. Wiring work for the main switchboard is finished. The relevant pumps test is acceptd. 3. lsolation test with 500 V megger 4. Test content and procedure Test of generator protection a. D/Gen.1, Data: 2125 kVA, 1700 kW, 450 V, 2726 A, 60 Hz , Power Factor: 0.8 Setting Delay S Result Reverse power -5% -85 KW 5 s Pre-alarm Reverse power -10% -170 KW 5 s Trip ACB Pref.trip step 1 2726 A 5 s T