25-Oct-2004 G. Ginther 2004 Shutdown Update Weeks 8 and 9 G. Ginther On behalf of the D0 Collaboration 25-October-2004 Week 8 Breaker maintenance on Monday October 11 Maintenance of emergency power deferred to minimize risk while membrane isolating SMT is down Prep for Layer 0 aperture survey remainder of week Disconnect Be beampipe joints and install purges on Be and EC beampipes ESH performed wipes of Be beampipe Install support structures for survey equipment Tracker Region Week 9 Layer 0 Aperture Survey Install survey equipment Perform survey Evaluation of results in progress Modificati