00-TAA-ABG-107002-00 Subcontractor Qualification Evaluation Procedure
ENGINEER’S STAMP: CONTRACTOR’S STAMP:
The Contractor declares that this submission has passed the contractor’s QA/QC
procedure and is in accordance with the requirements of the Contract.
Signature
AD For Approval CZ CZ MPJ
AC For Approval CZ CZ MPJ
AB For Approval CZ FM MPJ
AA For Approval GC FM
REV DESCRIPTION PREPARED CHECKED APPROVED DATE
P?YRY ENERGY AG
SEPCOIII ELECTRIC POWER CONSTRUCTION CORPORATION
PROJECT:
31002
LOCATION:
East Coast
PACKAGE:
“P” Power Plant
TITLE:
SUBCONTRACTOR QUALIFICATION EVALUATION PROCEDURE
SCALE:
None
DOCUMENT No.: REV:
AD 0 0 - T A A - A B G - 1 0 7 0 0 2 - 0 0
Engineer of Record
Sheet 1 of
14
PACKAGE “P” POWER PLANT
RAS AL KHAIR POWER AND DESALINATION PLANT – PHASE 1
Subject: SUBCONTRACTOR QUALIFICATION EVALUATION
Page 2
of 14
Doc No.: 0 0 - T A A - A B G - 1 0 7 0 0 2 - 0 0
Rev. AD
SECTION INDEX
1? General??3?
2? Evaluation?Form?Process??3?
3? Evaluation?Criteria?Satisfactory/Unsatisfactory??4?
4? Contractor?Qualification?Status??5?
PACKAGE “P” POWER PLANT
RAS AL KHAIR POWER AND DESALINATION PLANT – PHASE 1
Subject: SUBCONTRACTOR QUALIFICATION EVALUATION
Page 3
of 14
Doc No.: 0 0 - T A A - A B G - 1 0 7 0 0 2 - 0 0
Rev. AD
1. General
Evaluating the subcontractor qualification submittal is the most important part of this process; this is
where the qualification status of the contractor is determined.
Each of the sections included in the contractor qualification form is an essential element of a basic
safety plan.
These guidelines are provided to minimize or eliminate any subjection that may occur during the
evaluation of the contractors program. Certain elements of the contractors program must be in place
and must meet strict guidelines, while in other elements, The guidelines are not as absolute.
2. Responsibility
ACCSEPCOIII
您可能关注的文档
- %Krause ICML2010 - Submodular dictionary selection for sparse representation.pdf
- (ISP图的画法可参考)等电点沉淀法回收蛋白的特性.pdf
- (MX-GC控制柜)).pdf
- (ppt) IBM Content Based Copy Detection System for TRECVID 2009.pdf
- (ppt)BEA Weblogic Server8.1 Web Service.pdf
- (Reactive Violet 5R) decolorising native acclimatised bacterial consortia.pdf
- (universal.pdf
- (全6章)HL7 v3基础 Foundation完整版.pdf
- (初三英语测试题二).doc
- (天泉多级泵样本)TDLF-27p.pdf
最近下载
- 生物专业英语中英文对照(蒋悟生版)(Bioengineering English).pdf VIP
- 中高职衔接“3+2”人才培养方案模板(机电一体化技术)(高职).docx
- 基于微信小程序的校园导航系统设计与实现 毕业论文.docx
- 2025年陕西机电职业技术学院单招职业适应性测试题库word.docx VIP
- 团体标准住院患者身体约束护理PPT.pptx
- 20230313-平安证券-芯原股份-688521-国内半导体IP龙头,助力Chiplet技术发展.pdf VIP
- 小学残疾儿童送教上门教案(40篇).pdf
- 新人教版2024高三一轮总复习Unit2HealthyLifestyle课件选择性必修第三册(英语).pptx VIP
- 中高职衔接“3+2”人才培养方案模板(机电一体化技术 )(高职).pdf
- 北师大版小学数学三年级下册第二单元复习课.pptx
文档评论(0)