carried out; 4) for spring hangers (included simple spring, hangers and constant support hangers) it should also be recognized as setting and locking of loads. 5) check the surface quality, folded layering and without cracks, rust and other defects. 5) after completion of the test and control drawing number one by one, by series baled. Color alloy steel parts, the parts marking installation location and rotation about the direction you want. 7.3.14. hangers installation 7.3.14.1 hanger layout a. a clear design of hanger should be installed strictly in accordance with the drawings and designs