双代号收集计划图小我进修总结(国外英文资料)
双代号网络计划图个人学习总结(国外英文资料)
Double codename network plan diagram personal learning summary
One. Network diagram elements
Node: the beginning, end, or connection of a job, also known as an event. The Arabic numeral representation of the band;
Arrow: the direction of the direction of the work; Virtual work with virtual arrows;
Line: the path between two nodes is called a line. The critical line is represented by a double arrow;
Working hours: the work code is usually written on the top or left side of the arrow line, and the working hours are usually written down or on the right side of the arrow line.
Second, the drawing rules of the network plan diagram
A network diagram allows only one start node and one end node; A pair of nodes can only have an arrow; No two-way arrows are allowed; No closed loop is allowed; The layout is reasonable, try to avoid the crossing of the arrows.
Three. The computation of network time
The calculated results of the working hours are usually set at the top or left side of the arrow line, as shown here:
ES (first time) EF (first time) TF
LS (time to start) LF (time to complete)
This step (as a premise) :
Calculate ES, EF (from start to finish)
ES = the maximum (default: ES = 0) of the previous process EF.
EF = ES + T (the working time of the current process)
Calculate the LS and LF of each process.
LF = the minimum value of LS (default: the LF = tail process)
LS = the current working procedures lf-t (the working time of the current process)
Determine the total working period (Td)
Td = LFn (LF)
Calculate the TF for each process
TF = the current processs LS = the current processs LF - current processs EF
Identify critical lines (critical processes)
All of the TF = 0 processes are critical and are represented by a double arrow
Calculate the FF for each process
FF = the minimum value of the following procedure ES - the current processs EF (default: FF = 0)
The composition of the two code network diagrams
(a) node
Double code network diagram conne