- 1、原创力文档(book118)网站文档一经付费(服务费),不意味着购买了该文档的版权,仅供个人/单位学习、研究之用,不得用于商业用途,未经授权,严禁复制、发行、汇编、翻译或者网络传播等,侵权必究。。
- 2、本站所有内容均由合作方或网友上传,本站不对文档的完整性、权威性及其观点立场正确性做任何保证或承诺!文档内容仅供研究参考,付费前请自行鉴别。如您付费,意味着您自己接受本站规则且自行承担风险,本站不退款、不进行额外附加服务;查看《如何避免下载的几个坑》。如果您已付费下载过本站文档,您可以点击 这里二次下载。
- 3、如文档侵犯商业秘密、侵犯著作权、侵犯人身权等,请点击“版权申诉”(推荐),也可以打举报电话:400-050-0827(电话支持时间:9:00-18:30)。
- 4、该文档为VIP文档,如果想要下载,成为VIP会员后,下载免费。
- 5、成为VIP后,下载本文档将扣除1次下载权益。下载后,不支持退款、换文档。如有疑问请联系我们。
- 6、成为VIP后,您将拥有八大权益,权益包括:VIP文档下载权益、阅读免打扰、文档格式转换、高级专利检索、专属身份标志、高级客服、多端互通、版权登记。
- 7、VIP文档为合作方或网友上传,每下载1次, 网站将根据用户上传文档的质量评分、类型等,对文档贡献者给予高额补贴、流量扶持。如果你也想贡献VIP文档。上传文档
查看更多
栈桥计划 2(国外英文资料)
栈桥方案 2(国外英文资料)
China railway 17 group co., LTD. 6 engineering co., LTD
Construction plan of piers bridge
1 the overall plan
According to the requirement of the construction period, combined with the actual situation of the village road, there are three main lines that need to cross the canal.
A walkbridge with a span of 27.6 meters is located in the village of chongfu, which has a span of 20 + 734.
Located in the upper garden, the distance is 19 + 990, which is a bridge with a span of 18.6 meters.
Located in the upper garden, a 42.6 meter walkway is set up for 19 + 910.
Construction techniques and construction methods of major engineering projects
Three pier construction scheme of the project are consistent, mainly includes the trestle type steel pipe pile foundation, bailey beam erection, GangDian beam laying and bridge panel and bridge deck attached facilities construction. Combined with the rich experience accumulated in the construction of piers, the construction of various engineering organizations is guaranteed, and the project is safe, high quality and high efficiency.
Currently in urgent need of the construction for Shen Hai high speed on both sides of the rack is located on the yuan village mileage of 19 + 990 erection of a span of 18.6 meters of piers and the garden village mileage for 19 + 910 erection of a span of 42.6 meters of the pier. The K19 + 910 pier is located on both sides of the canal, the base of the bridge is 0.5 meters thick, 6 meters long and 3 meters wide in C15 stone concrete. Φ 630 x 8 steel tube is used for the pier foundation, the pile length of 15 metres, lateral pile spacing of 2.45 meters, designed three rows of steel pipe pile, each row of three, a total of 9 root. The pile is strengthened by I18a, and the top cap beams are connected by 2I36a, with 8mm steel plates. The welding of the parts is firm, meet the requirement of strength, the design drawings of the piers are shown in the attachment diagram. K19 + 990 on both sides of th