路基施工工艺-三分部
路基施工 Earthwork construction
施工准备 construction preparation
= 1 \* GB2 ⑴ 路基工程开工前,进行路基边线的测量放样工作,确定路基用地范围及路基边桩。
Before the beginning of earthworks construction, survey the road edge line and set sample to assure the range of land as well as the foundation edge pile.
= 2 \* GB2 ⑵ 待清表完后,与工程师对管段内进行断面复测。
After clearing and grubbing, conduct the re-survey on section of length with the attendance of engineer.
= 3 \* GB2 ⑶ 为了保证施工方便,行车安全和路基稳定,在正式施工前,根据测量人员放样的路基边桩,做好清理原地面的工作。清理工作内容包括:砍伐和收集林木,拔掉树墩及树根、小树木、灌木丛、清除基底表面杂草、植被和腐蚀土、淤泥、疏松土壤。清表、砍树挖根后要及时通知监理工程师进行收方。
For the construction convenient, traff