楼板,梁钢筋的要求(Requirements for floor and beam reinforcement)
楼板,梁钢筋的要求(Requirements for floor and beam reinforcement)
Dark column content:
1.1 columns of steel on the root of the cement has been cleaned.
1.2, in order to ensure the location of the main column of the concealed column is accurate, the fixed distance frame control is adopted
Binding of 1.3 columns of steel bars:
The number of 1.3.1 column stirrups is determined according to the requirements of the drawing. The first stirrup is set at the end of the 50mm.
1.3.2 draw the stirrup line on the vertical bar, and then tie it up and down from the top to the bottom.
1.3.3 the joints of the stirrups