预应力张拉工艺流程(Prestress tensioning process).doc

预应力张拉工艺流程(Prestress tensioning process) Prestress tensioning process 1. Installation of prestressed system: 1. Bellows, anchor pads and connector installations: (1) installation of corrugated pipe: Prestressed corrugated pipe adopt plastic corrugated pipe, corrugated pipe strictly according to the requirements of design drawing location and installation, and want to locate steel corrugated pipe fixed firmly, in a straight line segments is about 0.3 meters tud fixed a U glyph, curve section of encryption, so as to avoid in the process of concrete pouring, corrugated pipe produce displacement, a