路基调研(Subgrade research) Basic engineering accident investigation report civil 102 Case a Project overview Beijing baisheng building phase ii project, deep foundation pit 15 The diameter of reinforced concrete filling pile is made of pile anchor support 800 mm Pile top elevation - 3.0 m The pile top is made of concrete and concrete beams 3 m High retaining brick wall, and Reinforced concrete structure column. Under the ring beam 2 m. Place a layer of bolt, with steel waist girder to fix the bolt, actually the bolt length 20 m. Angle, 15 C to 18 The anchor is the steel strand. The geological con