炼钢厂房拆除工程施工的方案

目 录 一、工程概况······································ 二、施工部署······································ 三、拆除难点······································ 四、拆除方案······································ 五、吊车选择······································ 六、电缆加固方案·································· 七、施工措施······································ 八、施工人员及机械部署···························· 九、安全文明保证措施······························ 一、工程概况 本工程为金鼎炼钢除尘改造项目,在原有炼钢厂房加料跨与转炉跨5~7轴新建3#50T转炉。在钢水接受跨及浇注跨新建一个4#连铸机。为保证3#转炉工程实施,按设计规划先对原有厂房进行依次改造,将渣跨区域的部分柱距由12米扩到24米;将原加料跨区域的部分柱距由12米扩到18米;将原转炉跨新增加3#转炉区域部分12米扩到18米;将新增加4#连铸机区域部分柱距由12米扩到24米。炼钢厂房拆除