工程重油发机组安装施工组织设计

电仪施工方案Scheme of electric and instrumental construcation 变压器安装 Tranformer installation 设备到达现场后的检查及保养 Checkings and mentainance of equipment after arrival 充氮运输的变压器油箱内氮气压力应在0.01~0.03Mpa之间,达不到此要求,则进一步检查变压器是否受潮;如受潮应与厂家联系,并必须在安装前对变压器进行干燥处理,并做好检查及处理记录; If the transformers are carried by means of niteogen-filled transportation, the pressure inside its oil tank should remain stable between 0.01 to 0.03 Mpa. Otherwise further humidity ckecking is needed. If the transformer is humidified, it is necessary to connect the supplier. Moreover, drying work, checking and record-making must be carried out before