Project: Reem Island Sector 23 Shore Protection Works
PAGE
China Harbour Engineering Co. L.L.C.
SAFETY PLAN
Method Statement for
Dewatering
(M.S. –005–2.0)
China Harbour Engineering Co. L.L.C.
MS-0052.017/03/2009R.N.RevisionSubmit. DatePrepared ByChecked ByApproved By
General Introduction of Construction
General
Reem Island Development Sectors 2 3 Shore Protection Works has a total length of more than 6000 meters. The scope of work includes:Block Type Wall Structure、Shore Protection Wall Structure、Beach Works、Webbed L-Shaped Wall Structure(-3.25m、-2.5m)and can