某水电站坝址工程地质条件比选
Comparison of Geological Conditions of a Hydropower Dam Engineering
杜斌 DU Bin;叶怡狮 YE Yi-chong
(浙江省水利水电勘测设计院,杭州310002)
(Zhejiang Design Institute of Water Conservancy amp; Hydropower Power, Hangzhou 310002, China)
摘要:木文对某水电站工程拦河坝上下游坝址的工程地质条件从地形地貌、 地质构造、岩体风化卸荷、坝基防渗处理等方面进行比较,经过综合分析,推荐 上坝址为代表性坝址。
Abstract: This paper compared the engineering geological conditions of upstream and downstream dam of a hydropower dam project barrage from the topography, geological structure, rock weathering unloading, dam foundation seepage, etc. After a comprehensive analysis, it proposed that the upp