MS106 Date: 20/06/2009
Method Statement
FOR: Cement silo concrete casting scheme
水泥库施工方案
Owner: Lafarge
Contractor: CBMI
Established by:
Checked by:
Safety manager:
Owner Approve(Site Manager) : □yes □yes with comment
□ NO
Safety Manager : □ yes □yes with comment
□ NO
CBMI Construction Co., LTD.
Uganda Project
Version:1
MS001? ? ? ? ? ? ? ? ? ? ? ? ? ? ? ? ? ? ? DATE 05/5/08
? ? ? ? ? ?
Method Statement
For : Excavation less than 2 meters
Owner : Lafarge
Contractor: CBMI
Establi
Safety manager:
Owner Approve(Site Manager) : □yes? □yes with comment
□ NO
Safety Manager? :? □ yes? ? ? □yes wit