厂房钢筋施工方案2013年-11-29.docVIP

  • 1
  • 0
  • 约2.15万字
  • 约 32页
  • 2020-03-09 发布于浙江
  • 举报
南京中电熊猫液晶显示科技有限公司 G108项目3A阵列厂房 钢 筋 工 程 施 工 方 案 编制:  审核:  批准:  中天建设集团有限公司 2 0 1 3年 11月20日 目 录 1、编制依据········································1 2、工程概况········································1 3、结构简介········································2 4、施工准备········································4 5、钢筋接头方法及技术措施··························9 6、钢筋工程安装施工································16 7、钢筋工程成品保护措施····························24 8、质量保证措施····································25 9、安全保证措施····································30 10、环保措施·······································31 1、编制依据 本工程项目施工图纸、图纸会审和联系单; 本工程施工组织总设计; 《钢筋机械

文档评论(0)