路基碾压施工方案解析.docxVIP

  • 29
  • 0
  • 约2.86千字
  • 约 12页
  • 2021-01-17 发布于天津
  • 举报
路基碾压施工方案 WATER AND POWER DEVELOPMENT AUTHORITY KEYAL KHWAR HYDROPOWER PROJECT CONTRACT KKHPP-02 Keyal Khwar Hydropower Project in Pakistan Method Statement for Subgrade Rolling Compaction Construction of Keyal Valley Road and Patan-tunnel Road File Number: KKHPP-C2 -MS- 00 Document Preparation, Verification and Approval Name in Pr int Sig n Prepared by Tech ni cal Engin eer Wan g.x.k Checked by Tech ni cal Dep. Man ager Lvsheng Verified by Chief Engin eer Lvsheng Approved by Project Man ager Hel in Docume nt Revisi on Table Date (dd-mm-yy) Rev. No. Descripti on of Modificati on s/Revisi ons

文档评论(0)

1亿VIP精品文档

相关文档