UPGRADING OF 78 KM OF KASABA TO LUWINGU VIA CHUNGU (RD429) ROAD IN NORTHERN PROV E OF ZAMBIA The Mobilization Schedule of nel, Equipment and Material NO Description Dura Start Finish Unit ty 2015 11 12 1 2 3 4 5 6 7 8 B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B 1 Mobilization schedule of nel 159 d 2015/1/1 2015/6/8 1/1 1/1 6/8 2 Superintendent 100 d 2015/1/1 2015/4/10 32 1/1 4/10 3 Project manager 7 d 2015/1/1 2015/1/7 1 1/1 1/7 4 Construction Manager 7 d 2015/1/1 2015/1/7 1 1/1 1/7 5 Contract Manager 7 d 2015/1/1 2015/1/7 1 1/1 1/7 6 Equipment Manager 7 d 2015/1/1 2015/1/7 1 1/1 1/7 7