威海国际商品交易中心
施工组织总设计之二
总体暨电气篇
工程名称:威海国际商品交易中心
责任人:李刚
编制人:卢绪年
日期:2005年1月5日
一、编制根据··············································3
二、工程概况··············································3
三、施工组织机构与职责····································4
1、项目部组织机构示意图···································4
2、兼职状况阐明···········································5
3、职责··················································5
四、施工布署··············································7
1、施工次序···············································7
2、施工布署···············································7
3、工期计划安排···········································8
4、劳动力组织·············································8
五、基础设施和工作环境····································9
1、设备需用量及劳动力等供应计划···························9
2、安全用电技术措施·······································10
3、临时设施施工计划·······································12
六、施工技术措施··········································12
1、重要分部分项工程施工措施·······························12
2、治理质量通病措施·······································14
3、各工种施工配合·········································15
七、施工质量保证措施······································16
1、质量管理目旳···········································16
2、质量保证体系···········································16
3、以顾客为关注焦点·······································17
4、文献规定···············································17
5、人力资源控制···········································20
6、采购···················································20
7、机械设备、周转器材及监视和测量装置·····················20
8、施工过程控制············································21
9、产品监视和测量··········································22
10、分析改善···············································22
八、环境安全管理···········································23
(一)环境安全管理组织·····································23
(二)环境安全管理·········································23
(三)环境保护·············································27
(四)、文明施工管理········································28
九、工期保证措施···········································29