(1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activites and connects them with arrows that asow the dependencies.
This method includes following types of dependcies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion of the predecessor activity.
(3) is initiation of the successor activity, depends upon the initiation of the predecessor activity.
(1) A.PDM B.CPM C.PERT D.AOA
(2) A.F-S B.F-F C.S-F D.S-S
(3) A.F-S
您可能关注的文档
最近下载
- JGJ-T304-2013:住宅室内装饰装修工程质量验收规范.pdf VIP
- Join In 剑桥版五年级英语下册课件《Unit 6 第4课时(Parts 4a, 4b & 5)》.pptx VIP
- 《计算机控制技术第3版》-于海生 习题解答.pdf VIP
- 专题 力学综合压轴题 中考物理.docx VIP
- 2026年北京市通州区高三一模英语试卷(含答案).docx
- Join In 剑桥版五年级英语下册课件《Unit 5 第4课时(Parts 5 & 6)》.pptx VIP
- 备婚婚礼策划筹备准备流程清单.xlsx VIP
- 富士康-NPI新产品导入培训资料.pdf
- 一种临边作业用安全带挂点装置.pdf VIP
- Join In 剑桥版五年级英语下册课件《Unit 6 第1课时(Parts 1a, 1b & 1c)》.pptx VIP
原创力文档

文档评论(0)