PMP.PMI-001 题库

PMP PMI-001 Project Management Professional QUESTION 1 You are in process of identifying and documenting the project roles and responsibilities and create staffing management plan. All of the following should be addressed when listing the roles and responsibilities EXCEPT: Competency A. Authority B. Responsibility C. Compliance D. Role E. Answer: D Section: (none) Explanation/Reference: QUESTION 2 Reserve analysis is a tool /technique in all of the following processes EXCEPT: Cost budgeting A. Activity resource estimation B. Risk monitoring and control C. Activity duration estimation