NS2.1amp;2.2-HandoverList0427.doc
HANDOVER PROCEDURE竣工交接程序
Mechanical Completion and Pre-Commissioning Tests
竣工和单体试车
1. SCOPE范围
This document prescribes procedure for hand over at time of Mechanical Completion and division of responsibilities between the Owner and the Contractor for the activities involved in the hand over of the Plant, or any portion thereof, constructed by the Contractor in accordance with the Contract.
本文件明确了竣工交接时业主和承包人的责任范围,竣工的工程可以是整个项目,也可以是以合约规定由承包商完成的部分分项目。
2. TIME AND ACTIVITIES OF HAND OVER竣工交接的时间及相关工作
Handover shall take place at the time of Mechanical Completion between Owner and Contrac