2.2.3.2.4.桥梁上部构造施工
本标段主线桥梁上部构造的梁体分别是25m、40m后张预应力T梁,立交桥梁上部构造的梁体分别是25m后张预应力箱梁、30m后张预应力T梁以及现浇连续箱梁。根据现场实际情况,分别在每座桥的桥头处设置预制场,待桥头路基基本成型后开始预制,预制底座数量根据预制梁片量和工期要求设置。预制梁模板用定型大块钢模。预制梁运输用轨道平车运输,用架桥机安装。现浇连续箱梁采用满堂支架现浇。
2.2.3.2.4. Bridge Superstructure Construction ??? The main line bridge tenders of the upper structure of the beam is 25 m, 40m post-tensioned T-beam, the upper beam overpass structure of the beam is 25 m post-tensioned box girder, 30 m post-tensioned T-beam and continuous cast-in-place Box Girder. In accordance with the actual situation at the scene, in each bridge to install prefabricat