索网幕墙通过室内外手架配合进行安装

索网幕墙通过室内外脚手架配合进行安装。 Cable-net curtain wall will be erected under the cooperation of indoor and outdoor scaffoldings. 2.1安装流程测量放样→安装→索网安装→调整→玻璃安装→调整→清洁打胶。→ Steel column installation→ Cable net installation→ Adjustment→ Glass installation→ Cleaning and sealant installation 2.2测量放样首先依据总包单位的±0.000以及轴线进行复核。复核完毕,符合要求后,依据轴线与垂直索相对位置,进行拉索平面校准,将垂直索线弹在地面上,如图示。±0.000 of the general contracting work unit and axial line. If it meets the requirements after double check, conduct cable plane calibration as per axial line’s relative position with the vertical cable and snap the vertical cable line onto the grou