1. The cumulative CPI has been shown to be relatively stable after what percentage of project completion? A. 5% to 10% B. 15% to 20% C. 25% to 35% D. 50% to 75% 1. 在完成项目工作多少个百分比后,累计成本绩效指数相对稳定? A. 5% to 10% B. 15% to 20% C. 25% to 35% D. 50% to 75% 2. A project is considered complete when –- A. BAC = PV B. EV = AC C. PV = AC D. BAC = EV 2. 当----时一个项目可以认为完成了? A. BAC = PV B. EV = AC C. PV = AC D. BAC = EV 3. The project sponsor told the PM that he wanted to cut the 6 month project to 3 months by doubling the number of resources. The PM was experienced enough to know this would NOT work because of