Prof. Awad Hanna Prof. Awad Hanna Estimating Activity Duration Time Interval Time Interval is selected according to the nature of the activity (seconds - minutes…) It is common practice in construction industry to use calendar day. Use one and only one time unit for any schedule. Estimating Activity Duration 1. From company’s record 2. From standard estimating guide 3. Interviewing field personnel. Weather and Contingency Allowance Two approaches for assignment of weather allowance: 1. Add the Weather Allowance at the end of the project as a separate activity. 2. Add Weather Allowance to those