特殊条款[精选]
Contract PART 2
“合同” 第二部分
SPECIAL TERMS AND CONDITIONS
特殊条款与条件
The following special terms and conditions are hereby incorporated into the Contract and shall be applied to the Articles as indicated.
下列特殊条款条件已经并入合同适用于的条款。
Add the following sub-Article to Contract PART 1 Article 3. RESPONSIBILITIES OF CONTRACTOR: 第3承包商责任中加入下
.1 Performance Security Amount. The Contractor shall provide a Performance Bond, from an Owner approved financial institution, prior to the start of any Work. Such Bond shall be effective during the entire period of Contractor’s performance of the Work up until Final