- 1、本文档共23页,可阅读全部内容。
- 2、原创力文档(book118)网站文档一经付费(服务费),不意味着购买了该文档的版权,仅供个人/单位学习、研究之用,不得用于商业用途,未经授权,严禁复制、发行、汇编、翻译或者网络传播等,侵权必究。
- 3、本站所有内容均由合作方或网友上传,本站不对文档的完整性、权威性及其观点立场正确性做任何保证或承诺!文档内容仅供研究参考,付费前请自行鉴别。如您付费,意味着您自己接受本站规则且自行承担风险,本站不退款、不进行额外附加服务;查看《如何避免下载的几个坑》。如果您已付费下载过本站文档,您可以点击 这里二次下载。
- 4、如文档侵犯商业秘密、侵犯著作权、侵犯人身权等,请点击“版权申诉”(推荐),也可以打举报电话:400-050-0827(电话支持时间:9:00-18:30)。
查看更多
模板施工方案-技术标
模
板
施
工
方
案
二〇一六年十二月
目 录
一、编制依据 ··········································1
二、工程概况 ··········································1
三、施工部署 ···········································1
3.1模板选型及数量···································1
四、模板设计 ··········································3
4.1 墙(柱)体模板··································3
4.2 平台模板·········································3
五、施工准备··········· ·································3
5.1 材料及主要工具··································3
5.2 作业条件·········································3
六、施工工艺 ··········································4
6.1基础导墙模板·····································4
6.2组合竹夹板墙模···································5
6.3大模板墙模·······································6
6.4梁、顶板模板·····································10
6.5楼梯模板········································11
6.6施工缝留置······································12
6.7模板拆除········································14
七、模板施工质量标准及质量保证措施·······················15
7.1模板施工质量标准································15
7.2 模板施工质量保证措施····························16
八、模板施工质量通病与防治·······························17
九、成品保护·············································17
十、安全生产、文明施工注意事项··························17
十一、附图···············································19
模板工程施工方案
一、编制依据
1、漳州歌剧院项目施工图纸
2、《混凝土结构工程施工质量验收规范》(GB50204-2002)(2012版)
3、《混凝土结构工程施工规范》(GB50666-2002)(2011版)
二、工程概况
三、施工部署
1、模板选型及数量
1.1地下室墙模:地下室墙柱采用10厚竹胶合板及钢柱模施工,竹胶板主要规格为1220×2440mm,对拉螺栓采用直径为12mm的Ⅰ级钢制作。
1.2 主体结构墙柱模:采用法式钢制大模板,模板面板厚度为6mm;大模板制作由我公司模板厂根据施工需要在场外进行加工制作。
1.3 顶板、梁模板:采用10mm厚竹胶板,非标准层支撑采用扣件式脚手架可调支撑体系,立杆间距不大于1000mm,次龙骨间距不大于300mm;标准层采用碗扣式快拆体系。
1.4 楼梯踏步模板:楼梯采用10mm厚竹胶板制作根据图纸尺寸预先在场外定做;底模采用10mm厚竹胶板,支撑为钢管搭设,并配以可调支撑。
四、模板设计
1、墙(柱)体模板:
1.1组合竹夹板模板:组合竹夹板模板采用规格为1220*2440的板拼接;模板背楞采用φ48.3双钢管及50*100、50*50木方。组合模板采用钢管上、中、下三道斜撑;φ12螺杆对拉,螺杆间距450*600,第一道距地250,其余间距450,外墙采用止水螺杆(止水螺杆制作见止水螺杆示意图)。止水螺杆间距同内墙螺杆间距。
1.2钢大模板:大模板采用厚度为6mm的钢板制作。模板的规格以房间的尺寸为标准,采用整面墙(柱)组装式大模板(结合塔吊不同吊距上的吊重,大模板过长时可多块组装)。
大模板固定采用斜向钢管与地锚连接。垂直方向第一道距模板下口250mm,向上间距950mm一道;水平方向距模板侧边2